The expansion project has progressed over the past two weeks and we are now in a position where the new car park will be completed on Friday. This will mean that the builders are able to begin work on the top car park and in particular resourcing a gas pipe that runs around the top edge of this area. It is now clear that the middle school playground will not be split in half until the Easter holidays and the same is the case for the outdoor area outside reception – all significant works will be started when the children are not in school.
Below is a picture of the progress so far.
Below are two key people on the project. On the left is Jason O’Driscoll (he is the banksman) and on the right is our site manager, Russell Sullivan.
When I have further news I’ll be in touch. Thank you for your ongoing support.
Steve Taylor